|
News >Hurricane Rita
HURRICANE
RITA
Sam Houston Electric Cooperative continues
its Hurricane Rita system inspection and removal of damaged
powerline equipment.
According to Bernard Henderson,
Plant Engineer and Construction Manager Bill Townley, Sam
Houston EC is on schedule to complete this monumental task
this spring. More than 3,400 miles of distribution line were
damaged by the storm, as well as 2,300 poles.
Our contractor crews are in the field picking
up damaged transformers, regulators and capacitors," Henderson
said. "At this time, we're halfway through this process. Inspection
crews continue noting where the damaged transformers are,
which is speeding up the process.
Henderson said more than 500 transformers
have been picked up and expects contractor crews to remove
approximately 200-300 more as they make their way through
the service territory.
Members
who lived in areas subject to the cleanup received an insert
in their January bills detailing the work that would take
place near their homes and businesses. Contract workers are
moving through the Cooperative’s territory as efficiently
as possible.
| |
|
|
|
| |
Woodville
Operations Supervisor Mike Garess hangs a new flag above
the Tyler County Courthouse Thursday, marking the symbolic
completion of the restoration process.
|
|
|
The cleanup effort has picked up quite
a bit in the last couple of weeks since we have more people
in the field," Townley said. "Right now, we have removed more
than 90 percent of danger trees that were affecting our primary
distribution lines. Any trees that were leaning or had hanging
limbs over our distribution lines have been removed. We should
complete this task within a week."
Townley emphasized the Cooperative does
not remove trees that are near homes or service drops unless
they threaten the primary distribution system. Members are
responsible for removing trees on their property.
Crews continue to clean up broken poles,
scrap wire and insulators around the Cooperative’s 4,000
square mile territory.
"As
far as material clean up, we’ve completed 42 percent,"
Townley said. "Our inspectors have looked at 60 percent
of our lines. As soon as the inspections are complete, we
will be one step closer to restoring the system back to it
pre-Rita condition."
Click
here to see steps to restoring power.
Click
here to view our photo gallery.
Click here
to view Hurricane Rita Press Releases.
Oct.
14 - Noon - Flag raising marks end of restoration process

|